New Real Estate Projects in Oman 2026–2027: Launches and Handover Timeline
Which residential projects launched in Oman in 2026, which are announced but not yet selling, and which have a dated 2026 or 2027 handover — with sources, prices and ownership checks, updated monthly.

This guide tracks new residential projects in Oman for 2026 and 2027: what launched for sale this year, what has been officially announced but is not yet selling, and which developments have a dated handover milestone in 2026 or 2027. Every row is built from a dated source — a developer release, a government statement or a named publication — and every gap is shown as a gap.
- Last updated
- 14 November 2026
- Projects tracked
- 26
- Sources
- 42 dated references
- Next review
- December 2026
In short: 2026 brought a cluster of sales launches in Al Mouj, Muscat Bay, Jebel Sifah, Muscat Hills and Sultan Haitham City, and a new set of integrated tourism complex (ITC) agreements in Muscat that have not yet opened for sale. Only a handful of projects have a developer-stated handover date inside 2026, and we found no developer-confirmed handover date in 2027 — the 2027 dates in circulation come from agencies and listings. Expected handover dates are forecasts, not guarantees.
- 7sales launches in 2026
- 6announced, sales not yet open
- 4with 2026 handover milestones
- 4with 2027 handover reports
- 5with dates still to be confirmed
New Oman property projects at a glance
The table lists every project in this guide, grouped by milestone. Names link to a Homelist project page where one exists; bracketed numbers link to the sources. Ownership route describes the legal basis we could verify — see which projects allow foreign ownership.
| Project | Location / developer | Launch | Expected handover | Status | Starting price | Ownership route |
|---|---|---|---|---|---|---|
| Launched in 2026 | ||||||
| Luma Residences [1][2][34] | Muscat BayMuscat Bay (Omran Group) | 12 January 2026 | Not officially announced | Launched | Not publicly confirmed | Licensed ITC area |
| Olive Farms by Raya — Phase 2 [3][34] | Jebel SifahMuriya (Orascom Development & Omran) | January 2026 | Not officially announced | Launched | From OMR 77,2501-bedroom farmhouse · developer announcement, January 2026 [3] | Licensed ITC area |
| Azura Beach Residences III & IV [4][5][34] | Al Mouj MuscatAl Mouj Muscat | February 2026 | 2029developer brochure [42] | Launched | From OMR 69,000apartments · developer brochure on Homelist, not re-confirmed, 2026 [42] | Licensed ITC area |
| Golf Hills [7][41] | Muscat HillsAl Osool Hills / Al Osool Real Estate | Reported 1 March 2026 | Not officially announced | Launched | Not publicly confirmed | Not independently verified |
| Zaha Residence (Wadi Zaha) [8][13][37] | Sultan Haitham CityAl Ahly Sabbour | October 2026 | H2 2028developer statement [8] | Under construction | Not publicly confirmed | Sultan Haitham City scheme |
| W3 Apartments, Reem Villas & Jana Villas (Hay Al Wafa) [9] | Sultan Haitham CityAl Abrar Real Estate | October 2026 | Not officially announced | Launched | Not publicly confirmed | Sultan Haitham City scheme |
| SOCIO by The Lux Collective (Yenaier) [10] | Sultan Haitham CityAdanté Realty | October 2026 | Not officially announced | Launched | Not publicly confirmed | Not independently verified |
| Announced — sales launches still to come | ||||||
| Al Yazan Integrated Tourism Complex [19] | Muttrah, MuscatOmran Group & VA Group | Announced 9 November 2026 | Not officially announced | Announced | Not publicly confirmed | Licensed ITC area |
| Madinat Al Irfan — first Grova residential phase [20] | Madinat Al Irfan, MuscatGrova Developments (Hassan Allam) with Omran | Announced 13 October 2026 | Not officially announced | Announced | Not publicly confirmed | Not independently verified |
| Al Bustan ITC (Four Seasons residences) [21] | Al Bustan, MuscatOmran Group | Announced 26 March 2026 | Not officially announced | Announced | Not publicly confirmed | Licensed ITC area |
| Rawasi ITC (Jabal Bousher) [22] | Jabal Bousher, MuscatNot yet named | Announced May 2026 | Not officially announced | Announced | Not publicly confirmed | Licensed ITC area |
| Retal — Zones 3, 15 & 17, Sultan Haitham City [17] | Sultan Haitham CityRetal | Announced 13 May 2026 | Not officially announced | Announced | Not publicly confirmed | Sultan Haitham City scheme |
| Jood (Talaat Moustafa Group) [18][13] | Sultan Haitham CityTalaat Moustafa Group | Announced 7 October 2025 | Not officially announced | Announced | Not publicly confirmed | Sultan Haitham City scheme |
| Handovers expected in 2026 | ||||||
| Hay Al Wafa — first phase [12][13][14][9] | Sultan Haitham CityAl Abrar Real Estate | Construction from September 2024 | From December 2026developer statement [9] · Earlier stated: Mid-2026 [12] | Near handover | Not publicly confirmed | Sultan Haitham City scheme |
| Zen Residences [2][34] | Muscat BayMuscat Bay (Omran Group) | Before 2026 | Handover under way (reported January 2026)[2] | Completed / handing over | Not publicly confirmed | Licensed ITC area |
| The Sustainable City – Yiti [26][27][28] | Yiti, MuscatDiamond Developers / SEE Holding with Omran | Before 2026 | End of 2026developer statement [26] | Under construction | Not publicly confirmed | Licensed ITC area |
| AIDA — The Great Escape apartments & Phase 1 villas [23][24][25] | Yiti, MuscatDar Global with Omran | Before 2026 | Not confirmed — published dates conflictDeveloper target (May 2025): Q4 2026 [23][25] | Under construction | From OMR 117,000unit type not stated · developer brochure on Homelist, not re-confirmed, 2026 [42] | Licensed ITC area |
| Handovers reported for 2027 | ||||||
| Uptown Muscat [32] | Knowledge Oasis, Al KhoudWujha Real Estate Development | Before 2026 | Q1 2027agency-reported, not developer-confirmed [32] | Status unverified | Not publicly confirmed | Not independently verified |
| Golf Links [42][34] | Al Mouj MuscatAl Mouj Muscat | Before 2026 | 2027listing-reported, not developer-confirmed [42] | Status unverified | Not publicly confirmed | Licensed ITC area |
| Jinan Island [42][34] | Al Mouj MuscatAl Mouj Muscat | Before 2026 | 2027listing-reported, not developer-confirmed [42] | Status unverified | Not publicly confirmed | Licensed ITC area |
| Bellevue [42][34] | Al Mouj MuscatIdeal Buildings | Before 2026 | 2027listing-reported, not developer-confirmed [42] | Status unverified | Not publicly confirmed | Licensed ITC area |
| Dates still to be confirmed | ||||||
| Sarooj Oasis [16][13] | Sultan Haitham CitySarooj Construction Company | Reported 6 January 2025 | Not officially announced | Under construction | From OMR 31,600apartments · launch price — may have changed, January 2025 [16] | Sultan Haitham City scheme |
| Yenaier Homes [11][13] | Sultan Haitham CityAdrak Developers / Adanté Realty | Reported 25 November 2024 | Not officially announced | Under construction | Not publicly confirmed | Sultan Haitham City scheme |
| Vistal by Victoria Swarovski [29][34] | Al Mouj MuscatLEO Developments | Reported 10 December 2025 | Not officially announced | Launched | Not publicly confirmed | Licensed ITC area |
| Opal Residence [30][41] | Muscat HillsAl Nama Real Estate | Reported 7 May 2025 | Not officially announced | Status unverified | Not publicly confirmed | Not independently verified |
| La Vie Residences [31][41] | Muscat HillsORIS (Ominvest) | Reported 14 March 2023 | Not officially announced | Status unverified | Not publicly confirmed | Not independently verified |
Oman real estate project launch timeline — 2026
The timeline shows sales launches, announcements and handover milestones from mid-2025 onward. Dates keep the precision of the source: a developer that says "2029" is shown as 2029, not a guessed month.
- Sales launch
- Announcement
- Handover
- Original handover target
H2 2025
- Announced
Announcement7 October 2025
Jood (Talaat Moustafa Group)
Sultan Haitham City · Talaat Moustafa Group
- Launched
H1 2026
- Launched
- Launched
Sales launchJanuary 2026
Jebel Sifah · Muriya (Orascom Development & Omran)
- Completed / handing over
HandoverHandover under way (reported January 2026)
Zen Residences
Muscat Bay · Muscat Bay (Omran Group)
- Launched
- Launched
Sales launchReported 1 March 2026
Golf Hills
Muscat Hills · Al Osool Hills / Al Osool Real Estate
- Announced
Announcement26 March 2026
Al Bustan ITC (Four Seasons residences)
Al Bustan, Muscat · Omran Group
- Announced
Announcement13 May 2026
Retal — Zones 3, 15 & 17, Sultan Haitham City
Sultan Haitham City · Retal
- Announced
AnnouncementMay 2026
Rawasi ITC (Jabal Bousher)
Jabal Bousher, Muscat · Not yet named
H2 2026
- Announced
Announcement13 October 2026
Madinat Al Irfan — first Grova residential phase
Madinat Al Irfan, Muscat · Grova Developments (Hassan Allam) with Omran
- Under construction
Sales launchOctober 2026
Zaha Residence (Wadi Zaha)
Sultan Haitham City · Al Ahly Sabbour
- Launched
Sales launchOctober 2026
W3 Apartments, Reem Villas & Jana Villas (Hay Al Wafa)
Sultan Haitham City · Al Abrar Real Estate
- Launched
Sales launchOctober 2026
SOCIO by The Lux Collective (Yenaier)
Sultan Haitham City · Adanté Realty
- Announced
Announcement9 November 2026
Al Yazan Integrated Tourism Complex
Muttrah, Muscat · Omran Group & VA Group
- Near handover
HandoverFrom December 2026
Hay Al Wafa — first phase
Sultan Haitham City · Al Abrar Real Estate
- Under construction
Original handover targetQ4 2026
AIDA — The Great Escape apartments & Phase 1 villas
Yiti, Muscat · Dar Global with Omran
- Under construction
HandoverEnd of 2026
Yiti, Muscat · Diamond Developers / SEE Holding with Omran
H1 2027
- Status unverified
2027 — month not announced
- Status unverified
- Status unverified
- Status unverified
2028 and later
- Under construction
HandoverH2 2028
Zaha Residence (Wadi Zaha)
Sultan Haitham City · Al Ahly Sabbour
- Launched
Seven residential sales launches in 2026 are documented. The year opened with Muscat Bay's Luma Residences and Olive Farms Phase 2 at Jebel Sifah, followed by the last two Azura phases at Al Mouj and Golf Hills in Muscat Hills. October's Urban October exhibition in Muscat brought three Sultan Haitham City launches at once, alongside agreements the ministry valued at more than RO 1 billion [33].
Luma Residences
Launched
- Developer
- Muscat Bay (Omran Group)
- Location
- Muscat Bay
- Size
- 240 units · apartments, townhouses, and villas
- Launch
- 12 January 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Unveiled on 12 January 2026 under the patronage of the Minister of Housing and Urban Planning: about 240 freehold apartments, townhouses and villas on roughly 37,000 m² of built-up area, an investment of about RO 20 million. Initial bookings were reported above 50% at launch. No handover date or price list was published [1][2].
Olive Farms by Raya — Phase 2
Launched
- Developer
- Muriya (Orascom Development & Omran)
- Location
- Jebel Sifah
- Size
- Not published · farmhouses
- Launch
- January 2026
- Expected handover
- Not officially announced
- Starting price
- From OMR 77,2501-bedroom farmhouse · developer announcement, January 2026 [3]
- Ownership route
- Licensed ITC area
Muriya opened Phase 2 in January 2026 after Phase 1 sold out. The announcement quoted 1-bedroom farmhouses from OMR 77,250 and 2-bedroom farmhouses from OMR 123,600; it gave no handover date [3]. Jebel Sifah is one of the licensed ITCs named in ministry figures [34].
Azura Beach Residences III & IV
Launched
- Developer
- Al Mouj Muscat
- Location
- Al Mouj Muscat
- Size
- 611 units · apartments and chalets
- Launch
- February 2026
- Expected handover
- 2029developer brochure [42]
- Starting price
- From OMR 69,000apartments · developer brochure on Homelist, not re-confirmed, 2026 [42]
- Ownership route
- Licensed ITC area
The final two Azura phases: 570 apartments and 41 four-bedroom duplex chalets in the Marsa district. The launch materials describe freehold ownership for all nationalities [4][5]. The announcements give no handover date; the developer brochure we hold shows 2029. For comparison, Azura 2 (October 2025) was said to need about three years [6].
Golf Hills
Launched
- Developer
- Al Osool Hills / Al Osool Real Estate
- Location
- Muscat Hills
- Size
- 366 units · apartments
- Launch
- Reported 1 March 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
Three towers with 366 one- to three-bedroom apartments, reported on 1 March 2026 and offered freehold to Omanis and expatriates according to the developer. No price or handover date was published [7]. Muscat Hills has been described as an ITC [41]; we have not seen this project's own licence.
Zaha Residence (Wadi Zaha)
Under construction
- Developer
- Al Ahly Sabbour
- Location
- Sultan Haitham City
- Size
- 350 units · studios and apartments
- Launch
- October 2026
- Expected handover
- H2 2028developer statement [8]
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
Al Ahly Sabbour's first Oman project, presented at Urban October 2026: studios to three-bedroom apartments of 39–128 m², about 350 units under construction, first deliveries planned for the second half of 2028. The developer says buyers can apply for residency after paying 30% of the unit value, subject to Omani rules [8][37].
W3 Apartments, Reem Villas & Jana Villas (Hay Al Wafa)
Launched
- Developer
- Al Abrar Real Estate
- Location
- Sultan Haitham City
- Size
- Not published · studios, apartments, and villas
- Launch
- October 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
Three new releases in Hay Al Wafa launched at Urban October 2026: W3 (studios, one- and two-bedroom apartments), Reem Villas and Jana Villas. The developer describes them as freehold for all nationalities; no prices or project-specific handover dates were published [9].
Sources: [9]
SOCIO by The Lux Collective (Yenaier)
Launched
- Developer
- Adanté Realty
- Location
- Sultan Haitham City
- Size
- Not published · branded residences
- Launch
- October 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
Branded residences forming the final phase of Yenaier, launched at Urban October 2026 with hotel services by The Lux Collective. Unit numbers, prices, handover and ownership terms were not published [10].
Sources: [10]
New property projects announced for 2027 and beyond
No developer has published a firm 2027 sales-launch date for a new residential project that we could verify. What exists is a pipeline of signed agreements and announcements made in 2025–2026 whose sales could open in 2027 or later. They are listed here as Announced: an agreement or unveiling is not a sales launch, and none of these has a published price list.
Al Yazan Integrated Tourism Complex
Announced
- Developer
- Omran Group & VA Group
- Location
- Muttrah, Muscat
- Size
- 1,500 units · apartments and penthouses
- Launch
- Announced 9 November 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Unveiled on 9 November 2026 by Omran Group and VA Group: about 1,500 homes on 18.5 hectares at Port Sultan Qaboos, from studios to four-bedroom penthouses. Phase one (two buildings) is expected within three years; enabling works were due to start before the end of 2026. The ITC status is stated to allow full foreign ownership [19].
Sources: [19]
Madinat Al Irfan — first Grova residential phase
Announced
- Developer
- Grova Developments (Hassan Allam) with Omran
- Location
- Madinat Al Irfan, Muscat
- Size
- Not published · apartments and branded residences
- Launch
- Announced 13 October 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
Grova Developments (Hassan Allam) signed agreements on 13 October 2026 for a residential neighbourhood (about USD 75 million) and a branded-residence project (about USD 40 million) with Omran. Enterprise reports the district as an ITC; we have not confirmed this for the project [20].
Sources: [20]
Al Bustan ITC (Four Seasons residences)
Announced
- Developer
- Omran Group
- Location
- Al Bustan, Muscat
- Size
- 91 units · branded residences
- Launch
- Announced 26 March 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
An integrated tourism complex agreement signed with the Ministry of Heritage and Tourism in March 2026: hotel, marina and 91 branded residences to be operated by Four Seasons. No sales launch or completion date has been announced [21].
Sources: [21]
Rawasi ITC (Jabal Bousher)
Announced
- Developer
- Not yet named
- Location
- Jabal Bousher, Muscat
- Size
- Not published · mixed-use with homes
- Launch
- Announced May 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
A ministry agreement signed in May 2026 for a mountain ITC of about 993,000 m² in Jabal Bousher, in four phases over 15 years (about RO 558 million), with a residential component. The developer and unit plan have not been published [22].
Sources: [22]
Retal — Zones 3, 15 & 17, Sultan Haitham City
Announced
- Developer
- Retal
- Location
- Sultan Haitham City
- Size
- 2,000+ units · apartments and villas
- Launch
- Announced 13 May 2026
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
Saudi developer Retal's first Oman venture: more than 2,000 villas and apartments in Zones 3, 15 and 17. It will sell off-plan; construction and sales were said in May 2026 to start "shortly", with completion projected within nine years [17].
Sources: [17]
Jood (Talaat Moustafa Group)
Announced
- Developer
- Talaat Moustafa Group
- Location
- Sultan Haitham City
- Size
- Not published · mixed-use with homes
- Launch
- Announced 7 October 2025
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
Talaat Moustafa Group's residential community in Sultan Haitham City, announced in October 2025. In May 2026 the ministry said construction was expected to start soon [18][13]. No sales prices have been published.
Expected property handovers in 2026
Four handover milestones fall in 2026. Only one is confirmed as under way (Zen at Muscat Bay); one is dated by its developer for December 2026 (Hay Al Wafa); one rests on a developer target published in 2025 (The Sustainable City – Yiti); and one has conflicting published dates (AIDA).
Hay Al Wafa — first phase
Near handover
- Developer
- Al Abrar Real Estate
- Location
- Sultan Haitham City
- Size
- 470 units · villas, townhouses, and apartments
- Launch
- Construction from September 2024
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
The first neighbourhood of Sultan Haitham City. Al Abrar Real Estate's first phase had 470 villas, townhouses and apartments, with construction from September 2024 and handovers first planned for mid-2026 [12]. The ministry later spoke of residents moving in from October 2026 [13] and by the end of 2026 [14]; in October 2026 the developer said handovers would begin in December 2026 [9]. The target has therefore moved by about six months.
Zen Residences
Completed / handing over
- Developer
- Muscat Bay (Omran Group)
- Location
- Muscat Bay
- Size
- Not published · apartments
- Launch
- Before 2026
- Expected handover
- Handover under way (reported January 2026)[2]
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Muscat Bay's Zen project was reported in January 2026 as about 90% sold and in its handover phase [2]. We have not found a completion figure for all units.
The Sustainable City – Yiti
Under construction
- Developer
- Diamond Developers / SEE Holding with Omran
- Location
- Yiti, Muscat
- Size
- Not published · apartments, townhouses, and villas
- Launch
- Before 2026
- Expected handover
- End of 2026developer statement [26]
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
In July 2025 the developer said full handover was on track for the end of 2026 [26]. Later releases — The Arc (132 residences) and the Plaza district (1,225 homes, financing signed in September 2026) — have no published handover dates [26][28]. Our project page lists 2027 for the units currently advertised, based on listings; that figure is not developer-confirmed.
AIDA — The Great Escape apartments & Phase 1 villas
Under construction
- Developer
- Dar Global with Omran
- Location
- Yiti, Muscat
- Size
- Not published · apartments and villas
- Launch
- Before 2026
- Expected handover
- Not confirmed — published dates conflictDeveloper target (May 2025): Q4 2026 [23][25]
- Starting price
- From OMR 117,000unit type not stated · developer brochure on Homelist, not re-confirmed, 2026 [42]
- Ownership route
- Licensed ITC area
Dar Global targeted handover of The Great Escape apartments and the Phase 1 villas for Q4 2026 when it awarded the main contract in May 2025 [23]. A later secondary report says the developer's page now shows June 2029 [25]; we could not open the developer page to confirm. Phase 1 infrastructure is due by 2027 and Trump International Oman is scheduled to open in December 2028 [24]. The OMR 117,000 figure comes from a developer brochure and does not name the unit type.
Expected property handovers in 2027
We found no developer or government statement fixing a 2027 handover for a residential project. The 2027 dates below come from an agency page and from current listings, so they are marked Status unverified. Treat them as questions to put to the developer, not as schedules. AIDA's Phase 1 infrastructure is also due by 2027 [24], which is not the same as homes being handed over.
Uptown Muscat
Status unverified
- Developer
- Wujha Real Estate Development
- Location
- Knowledge Oasis, Al Khoud
- Size
- Not published · apartments
- Launch
- Before 2026
- Expected handover
- Q1 2027agency-reported, not developer-confirmed [32]
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
Wujha's apartment project at Knowledge Oasis Muscat. An agency page reports a Q1 2027 handover and describes it as freehold but not an ITC, with owner residency not confirmed [32]. We have not found a developer or government statement confirming the date.
Sources: [32]
Golf Links
Status unverified
- Developer
- Al Mouj Muscat
- Location
- Al Mouj Muscat
- Size
- Not published · apartments
- Launch
- Before 2026
- Expected handover
- 2027listing-reported, not developer-confirmed [42]
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Apartments in Al Mouj; current listings report a 2027 handover, which we have not confirmed with the developer [42].
Jinan Island
Status unverified
- Developer
- Al Mouj Muscat
- Location
- Al Mouj Muscat
- Size
- 43 units · villas
- Launch
- Before 2026
- Expected handover
- 2027listing-reported, not developer-confirmed [42]
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Al Mouj Muscat's private island collection of 43 five- and six-bedroom villas. Listings report 2027 for completion; not developer-confirmed [42].
Bellevue
Status unverified
- Developer
- Ideal Buildings
- Location
- Al Mouj Muscat
- Size
- Not published · apartments
- Launch
- Before 2026
- Expected handover
- 2027listing-reported, not developer-confirmed [42]
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Apartment building in Al Mouj by Ideal Buildings; listings report a 2027 handover, not developer-confirmed [42].
Projects with dates still to be confirmed
These projects are on sale or under construction but have no published handover date. They are relevant because buyers see them advertised now; the right question for each is the contractual handover date in the reservation agreement.
Sarooj Oasis
Under construction
- Developer
- Sarooj Construction Company
- Location
- Sultan Haitham City
- Size
- 210 units · apartments and villas
- Launch
- Reported 6 January 2025
- Expected handover
- Not officially announced
- Starting price
- From OMR 31,600apartments · launch price — may have changed, January 2025 [16]
- Ownership route
- Sultan Haitham City scheme
Sales opened in January–February 2025 with 4-bedroom Ahed villas from RO 77,000 and Azha apartments from RO 31,600 at launch [16]. The ministry listed Sarooj Oasis among neighbourhoods under construction in May 2026 [13]. The launch material called it "ITC"; we have not confirmed an ITC licence. No handover date has been published.
Yenaier Homes
Under construction
- Developer
- Adrak Developers / Adanté Realty
- Location
- Sultan Haitham City
- Size
- 700+ units · studios and apartments
- Launch
- Reported 25 November 2024
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Sultan Haitham City scheme
Soft-launched in November 2024 with more than 700 studio to three-bedroom apartments [11]; the ministry reported construction under way in May 2026 [13]. No handover date has been published.
Vistal by Victoria Swarovski
Launched
- Developer
- LEO Developments
- Location
- Al Mouj Muscat
- Size
- Not published · apartments and chalets
- Launch
- Reported 10 December 2025
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Licensed ITC area
Victoria Swarovski–branded apartments and duplex chalets by LEO Developments, launched in December 2025 [29]. The developer's residency claim should be checked against Royal Oman Police rules [38]. No handover date was published; listings show 2029.
Opal Residence
Status unverified
- Developer
- Al Nama Real Estate
- Location
- Muscat Hills
- Size
- 279 units · apartments
- Launch
- Reported 7 May 2025
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
279 residential and 23 commercial units unveiled in May 2025 [30]. No handover date or prices were published; listings show 2029.
La Vie Residences
Status unverified
- Developer
- ORIS (Ominvest)
- Location
- Muscat Hills
- Size
- Not published · apartments and villas
- Launch
- Reported 14 March 2023
- Expected handover
- Not officially announced
- Starting price
- Not publicly confirmed
- Ownership route
- Not independently verified
ORIS (Ominvest) project with villas, flats and serviced apartments around a boutique hotel, unveiled in 2023 [31]. Listings report a 2026 handover; no developer confirmation found.
New developments by area
| Area | Documented 2026 activity | What to keep in mind |
|---|---|---|
| Al Mouj Muscat | Azura III & IV launched (Feb 2026) [4]; Vistal on sale since Dec 2025 [29] | Licensed ITC [34]. Several handover years in circulation come from listings, not the developer. |
| Muscat Hills | Golf Hills reported 1 March 2026 [7] | Opal and La Vie launched earlier; their handover dates are not published [30][31]. |
| Muscat Bay | Luma Residences launched 12 Jan 2026 [1]; Zen handing over [2] | Licensed ITC [34]. Luma has no published handover date. |
| Yiti | Sustainable City Plaza district financed (Sep 2026) [28] | Two ITC projects: The Sustainable City – Yiti and AIDA. Both have 2026 targets that need re-confirming. |
| Sultan Haitham City | Zaha Residence, Al Abrar's three Hay Al Wafa releases and SOCIO launched (Oct 2026) [8][9][10]; Retal agreement (May 2026) [17] | First residents due from December 2026 [9]. Ownership and residency terms vary by project. |
| Jebel Sifah | Olive Farms Phase 2 launched (Jan 2026) [3] | Licensed ITC [34]. Prices published at launch; no handover date. |
| Muttrah, Al Bustan, Jabal Bousher, Madinat Al Irfan | Al Yazan unveiled (Nov 2026) [19]; Al Bustan [21], Rawasi [22] and Irfan [20] agreements | Announced only — no sales launch, price list or handover date yet. |
Salalah and Hawana Salalah are absent because we found no dated 2026 residential launch or handover there; listings for existing Hawana phases continue. For a comparison of areas on prices, rents and access, see the best areas to invest in Oman.
Which new projects allow foreign ownership?
Foreign freehold ownership in Oman remains limited to designated frameworks [36]. The main route is the Integrated Tourism Complex (ITC), where non-Omanis can own freehold title [35]. Al Mouj, Muscat Bay, Jebel Sifah and Hawana Salalah are among the ITCs named in ministry figures [34]; The Sustainable City – Yiti and AIDA belong to the Yiti integrated tourism development. Our guide to integrated tourism complexes lists the known ITCs.
- Licensed ITC area — the project sits in a complex named as a licensed ITC in an official or ministry-sourced report. The project's own sales authorisation still has to be checked.
- Sultan Haitham City scheme — a government new-city project where developers state that units are sold to all nationalities. Terms are set project by project; the city as a whole is not an ITC.
- Not independently verified — the developer or an agency says foreigners can buy, but we have not seen the legal basis (for example Muscat Hills projects, Uptown Muscat, Madinat Al Irfan).
Residency is a separate question. A property-owner residence visa is issued by the Royal Oman Police under its own conditions [38]; Sultan Haitham City has its own route tied to paying 30% of the price [37]. A developer's marketing line about "permanent" or "lifetime" residency is not a guarantee — see residency through property and the foreign ownership guide.
Starting prices of new property projects in Oman
Most 2026 launches did not publish prices. The figures below are the only ones we could tie to a dated source. They are entry prices for the stated unit type at the stated date — not a promise that such a unit is still available.
| Project | Location | Published figure | Unit | Basis and date |
|---|---|---|---|---|
| Olive Farms by Raya — Phase 2 | Jebel Sifah | From OMR 77,250 | 1-bedroom farmhouse | developer announcement, January 2026 [3] |
| Azura Beach Residences III & IV | Al Mouj Muscat | From OMR 69,000 | apartments | developer brochure on Homelist, not re-confirmed, 2026 [42] |
| AIDA — The Great Escape apartments & Phase 1 villas | Yiti, Muscat | From OMR 117,000 | unit type not stated | developer brochure on Homelist, not re-confirmed, 2026 [42] |
| Sarooj Oasis | Sultan Haitham City | From OMR 31,600 | apartments | launch price — may have changed, January 2025 [16] |
For Sultan Haitham City as a whole, the Ministry of Housing and Urban Planning quoted prices of about RO 900 per m² for investors in February 2026 [15]. Brochure figures for Azura III & IV and AIDA come from developer brochures published on Homelist and have not been re-confirmed with the developers for this update. For prices in completed areas, see property prices in Oman; for the full cost of buying on top of the price, see property buying costs.
Ready vs off-plan: which new projects should buyers consider?
Almost every project in this guide is sold off-plan: you pay in stages against a building that does not yet exist, and the handover date is a contractual target. Off-plan typically offers staged payments and a choice of units; the trade-off is completion risk and a wait before any rental income. A completed or handing-over home lets you inspect the actual unit and title before paying in full.
- Off-plan suits buyers who can wait, want a payment plan and accept that dates may move. Check the escrow arrangements and the contract's delay clauses first — see buying off-plan property in Oman.
- Ready or near-handover suits buyers who need the property soon, plan to rent immediately or want to see what they are buying. Resale homes in established ITCs are an alternative to new launches.
- In both cases ask what is included (finishes, furniture, service charges) and when the title deed will be issued.
This guide does not rank projects or forecast returns. Rental yields by area are covered in rental yields in Oman.
How reliable are developer handover dates?
A handover date in a launch announcement is the developer's plan at that moment. Two projects in this guide already show how plans move: Sultan Haitham City's first handovers went from "mid-2026" in March 2025 [12] to "December 2026" in October 2026 [9]; AIDA's Q4 2026 target from May 2025 [23] is contradicted by a later report of June 2029 [25].
- Construction progress — a contract award or a groundbreaking is not proof that a building is on schedule. Ask for the latest progress report or site photos with dates.
- Developer announcements — dates in press releases are rarely updated publicly when they change.
- Regulatory approvals — under the Real Estate Regulation Law, developers and projects need licences from the Ministry of Housing and Urban Planning [39][40].
- Financing and execution — bank financing announcements (such as for Luma and the Yiti Plaza) show funding is arranged, not that delivery dates are fixed [1][28].
- Your contract — the binding date is the one in the sale and purchase agreement, together with any grace period and compensation clause.
How to verify a new project before paying
Run these checks before you sign a reservation form or transfer a deposit. Our detailed guide on checking an off-plan project in Oman explains each step.
- Developer identity — the legal company name and commercial registration match the contract and the bank account.
- Project approval — the developer holds a real estate development licence and the project its own project licence from the Ministry of Housing and Urban Planning [40].
- Ownership eligibility — the plot is inside an ITC or another framework that allows your nationality to own, and the contract states the title type.
- Sales authorisation — the project is permitted to be marketed and sold off-plan at this stage.
- Escrow — payments go into the project's escrow account, not a general company account [39].
- Reservation contract — refund terms for the deposit are written down before you pay it.
- Payment schedule — instalments are tied to construction milestones or dates you can verify.
- Expected handover — the contract gives a handover date, a grace period and what happens if it is missed.
- Refund conditions — what you get back if the project is cancelled, delayed beyond the grace period or changed.
- Written specifications — unit size, finishes, parking and service charges are attached to the contract, not only shown in a brochure.
What buyers should watch in 2027
Confirmed: Sultan Haitham City's first neighbourhood is due to start handovers from December 2026 [9], and Zaha Residence is scheduled for first deliveries in the second half of 2028 [8]. Al Yazan's enabling works were due to start before the end of 2026 [19]. For 2027 scenarios, drivers and dates to watch, see our Oman real estate outlook 2027, updated monthly.
Still to be confirmed: whether The Sustainable City – Yiti and AIDA meet or revise their 2026 targets; when Retal [17], Jood [18], Madinat Al Irfan [20], Al Bustan [21] and Rawasi [22] open for sale and at what prices; and whether the 2027 dates reported for Uptown Muscat and several Al Mouj projects are confirmed by their developers. We will add each change to this page with its date and source.
How this guide is updated
Inclusion criteria. A project is included if (a) its sales launched in 2026, (b) it was officially announced in 2025–2026 with sales still to come, (c) it has a dated 2026 or 2027 handover milestone, or (d) it is on sale now with an unconfirmed date and is relevant to buyers comparing new projects. Master communities are not counted as projects; each phase or building release is listed separately.
New launches and agreements are reported first in our monthly Oman real estate news roundup; once a project has verifiable details, it is added to this timeline.
Status definitions. *Announced* — officially unveiled, sales not open. *Launched* — sales launch confirmed. *Under construction* — construction supported by dated evidence. *Near handover* — a current source places handover within the next few months. *Completed / handing over* — completion or handover confirmed. *Delayed* — a published timeline changed, with evidence. *Status unverified* — current status cannot be established. Status labels describe the evidence, not quality or legal approval.
Monthly update. This page is reviewed every month at the same address. Each review re-checks developer announcements, new launches, handover changes, construction updates, prices and ownership claims, updates all four language versions together and changes the date at the top only after the facts have been checked. If a date changes, the new date is shown with the earlier one and the source of the change.
Browse current projects in our projects directory, compare developers, or read the quarterly Oman property market report for transaction data. More market coverage is in Market Trends.
Frequently asked questions
What are the newest property projects in Oman?
The most recent residential launches we could verify are Zaha Residence, Al Abrar's three Hay Al Wafa releases and SOCIO at Yenaier, all launched at Urban October 2026 in Sultan Haitham City. Al Yazan in Muttrah was unveiled on 9 November 2026 but is not yet on sale.
Which projects launched in Muscat in 2026?
Documented 2026 launches in Muscat Governorate are Luma Residences (Muscat Bay, January), Azura Beach Residences III & IV (Al Mouj, February), Golf Hills (Muscat Hills, reported March) and, in October, Zaha Residence, Al Abrar's Hay Al Wafa releases and SOCIO in Sultan Haitham City. Olive Farms Phase 2 at Jebel Sifah also launched in January.
What new residential developments are planned for 2027?
No firm 2027 sales-launch date has been published. Projects announced in 2025–2026 that could open for sale later include Al Yazan, Retal's Sultan Haitham City zones, Jood by Talaat Moustafa Group, Madinat Al Irfan's first Grova phase, Al Bustan and Rawasi.
Which Oman property projects will hand over in 2027?
We found no developer- or government-confirmed 2027 handover. Uptown Muscat (Q1 2027, agency-reported) and Golf Links, Jinan Island and Bellevue at Al Mouj (2027, listing-reported) carry 2027 dates that still need developer confirmation.
Can foreigners buy in new Oman developments?
Yes, in designated frameworks: mainly integrated tourism complexes such as Al Mouj, Muscat Bay, Jebel Sifah, Hawana Salalah and the Yiti projects, and in Sultan Haitham City projects whose developers sell to all nationalities. Outside these frameworks foreign ownership remains restricted.
Which projects are officially licensed ITCs?
Al Mouj, Muscat Bay, Jebel Sifah and Hawana Salalah are named as licensed ITCs in ministry figures, and The Sustainable City – Yiti and AIDA are part of the Yiti integrated tourism development. New ITC agreements in 2026 include Al Yazan, Al Bustan and Rawasi. Always ask for the specific project's licence.
What is the starting price of new apartments in Muscat?
Most 2026 launches did not publish prices. Published figures include Sarooj Oasis apartments from RO 31,600 at their 2025 launch, Azura III & IV from OMR 69,000 and AIDA from OMR 117,000 in developer brochures, and Olive Farms 1-bedroom farmhouses from OMR 77,250. Check current availability with the developer.
Can I buy an off-plan property in Oman?
Yes. Off-plan sales are regulated under the Real Estate Regulation Law: the developer and the project need licences and buyer payments should go into an escrow account. Read the contract's handover, delay and refund clauses before paying.
How can I verify a developer's handover date?
Ask for the date written in the sale and purchase agreement, the latest dated construction progress report and the project licence. Compare it with the developer's most recent public statement; a date in an old press release or a listing is not a commitment.
Are new projects eligible for property-owner residency?
Residency depends on Royal Oman Police rules and, in Sultan Haitham City, on the city's 30% payment route — not on a developer's marketing. Check the conditions that apply to your purchase price and payment stage before relying on residency.
What happens if a project is delayed?
Your rights depend on the contract and the Real Estate Regulation Law. Check the grace period, any compensation for late delivery and your right to cancel and recover payments held in escrow. Get independent legal advice in Oman if a delay occurs.
Where can I compare new property projects?
Use the table at the top of this guide for dates, status, prices and ownership, and browse Homelist's projects directory for photos, floor plans and listings in each project.
Last verified: Project launches, handover statements, prices and ownership claims checked on 14 November 2026 against the sources listed below. Next review: December 2026 (monthly).
This guide is general information, not investment, legal or financial advice. It does not rate developers or projects. Dates and prices are those published by the cited sources at the dates shown; availability, prices and timelines can change. Confirm everything with the developer, the Ministry of Housing and Urban Planning and an independent lawyer in Oman before paying.
Sources and references
- Oman Observer (12 Jan 2026) — Luma Residences unveiled at Muscat Bay with RO 20 million investment
- Muscat Daily (13 Jan 2026) — Muscat Bay launches Luma Residences; Zen project in handover phase
- Gulf News (Jan 2026) — Jebel Sifah unveils Phase 2 of Olive Farms by Raya (Muriya), starting prices
- Oman Observer (14 Feb 2026) — Azura Beach Residences 3 and 4 launched at Al Mouj Muscat
- Gulf Construction (1 Mar 2026) — Final phases of Al Mouj Muscat's Azura residences launched
- Oman Observer (29 Oct 2025) — Azura Beach 2: delivery expected within three years
- Gulf Construction (1 Mar 2026) — Al Osool unveils Golf Hills freehold residential project, Muscat Hills
- Times of Oman (7 Oct 2026) — Al Ahly Sabbour launches Zaha Residence, Sultan Haitham City
- Lovin Muscat (11 Oct 2026) — Al Abrar Real Estate launches three projects in Hay Al Wafaa; handovers from December 2026
- UK News Group (9 Nov 2026) — Adanté Realty launches SOCIO by The Lux Collective residences at Yenaier
- Oman Observer (25 Nov 2024) — Yenaier project unveiled in Sultan Haitham City
- Oman Observer (8 Mar 2025) — Sultan Haitham City: Al Wafa first phase, handovers planned for mid-2026
- Oman Observer (30 May 2026) — Al Wafa district to receive residents from October 2026; neighbourhoods under construction
- Gulf Construction (29 Sep 2026) — Sultan Haitham City: first residents expected in Hay Al Wafaa by end-2026
- Oman Observer (24 Feb 2026) — Sultan Haitham City first phase; prices about RO 900 per m² for investors
- Oman Observer (6 Jan 2025) — Sarooj Oasis launched at Sultan Haitham City, launch prices
- MEP Middle East (13 May 2026) — Retal to develop Zones 3, 15 and 17 of Sultan Haitham City
- Oman Observer (7 Oct 2025) — Talaat Moustafa Group to launch Yamal and Jood projects in Oman
- Oman Observer (9 Nov 2026) — Al Yazan ITC: RO 200 million waterfront project in Muttrah
- Enterprise (14 Oct 2026) — Hassan Allam's Grova signs first residential phase at Madinat Al Irfan
- Times of Oman (26 Mar 2026) — Agreement to develop an integrated tourism complex in Al Bustan, Muscat
- Gulf News (8 May 2026) — Rawasi integrated tourism complex agreement, Jabal Bousher
- Dar Global press release (7 May 2025) — Main works for The Great Escape apartments and AIDA Phase 1 villas; handover targeted for Q4 2026
- Gulf Construction (2025) — AIDA advances: Phase 1 infrastructure by 2027, Trump International Oman due December 2028
- Oman Verified (2026, secondary) — reports Dar Global now showing June 2029 completion for The Great Escape
- The Sustainable City – Yiti (23 Jul 2025) — The Arc launched; full handover on track for end of 2026
- Oman Observer (18 Sep 2024) — The Sustainable City – Yiti to be fully operational by 2026
- IFC (30 Sep 2026) — Financing for the Plaza district (1,225 homes) at The Sustainable City – Yiti
- Oman Observer (10 Dec 2025) — Vistal by LEO Developments launched at Al Mouj Muscat
- Times of Oman / ONA (7 May 2025) — Opal Residence unveiled in Muscat Hills
- Oman Observer (14 Mar 2023) — ORIS (Ominvest) unveils La Vie at Muscat Hills
- Tamlik (agency page, 2026) — Uptown Muscat: Q1 2027 handover, non-ITC freehold (agency information, not developer-confirmed)
- Oman Observer (5 Oct 2026) — Urban October exhibition opens with RO 1 billion in agreements
- Times of Oman (4 Jul 2023) — Ministry of Heritage and Tourism figures on licensed ITCs (Al Mouj, Muscat Bay, Jebel Sifah, Hawana Salalah)
- Times of Oman (25 Jul 2026) — Legal framework governing foreign ownership in Oman's ITCs
- Gulf News (Jun 2026) — Oman clarifies foreign property ownership remains restricted to designated areas
- Enterprise (30 Sep 2026) — Sultan Haitham City residency incentives (30% payment route)
- Gov.om / Royal Oman Police — Residence visa for property owners
- Royal Decree 79/2025 issuing the Real Estate Regulation Law — decree.om
- Gov.om / Ministry of Housing and Urban Planning — Real estate development project licence
- Oxford Business Group (2016) — Integrated tourism complexes in Oman (lists Muscat Hills)
- Homelist project pages — developer brochures and listing-reported handover years (observed 14 Nov 2026)